Refinancing a construction loan into a permanent mortgage: one closing or two, and what the second closing costs
On a two-time close, a new permanent mortgage pays off the construction loan, so the second closing is a refinance: Fannie Mae lets it close as a limited cash-out refinance, or as a cash-out refinance once you have held title to the lot for 6 months and meet the other cash-out rules, at whatever rate the market offers that week. A one-time close converts on terms written at the first closing, unless the lender modifies them before conversion, and can never take cash out. Between those two contracts sits a build that usually runs 9 to 12 months, and the 30-year average in Freddie Mac's survey moved from 3.22% in the week of January 6, 2022 to 6.49% in the week of December 1, 2022, a span of 10.8 months that added $791.40 to the monthly payment on a $400,000 loan.
Worksheet steps (10)
- One note or two: what changes when the house is finished
- Rules side by side: Fannie Mae's single and two-closing sections and FHA's two products
- The value the permanent loan is measured against
- FHA counts the lot by how long you have owned it
- Three clocks on the lot and the construction note
- What the second closing repeats, line by line
- Rate exposure during a 9 to 12 month build, at four past survey windows
- A single-close lock is less fixed than it looks
- Refinancing again after a one-time close has converted
- Picking the structure before the first draw
One note or two: what changes when the house is finished
Fannie Mae describes construction-to-permanent financing as a long-term mortgage that replaces the interim loan used to build a new residence, and its overview section, B5-3.1-01 (dated 06/04/2025), allows it to be structured with one closing or with two. Either way the borrower must hold title to the lot, bought earlier or as part of the deal, and every mechanic's and materialmen's lien must be paid and cleared before Fannie Mae buys the permanent loan. Attached condo units and all co-ops are ineligible; a detached unit in a condo project can be financed this way.
In a single-closing transaction the borrower signs once. Under B5-3.1-02 (dated 05/06/2026) the lender manages the draws to the builder, and because the loan documents already state the permanent terms, the construction loan converts on its own when the work is complete. Fannie Mae cannot buy the loan until that conversion has happened. The construction phase must be built as a temporary loan exempt from the federal ability-to-repay rule, which 12 CFR 1026.43(a)(3)(iii) grants to "a construction phase of 12 months or less of a construction-to-permanent loan." That is why Fannie Mae caps any single construction period at 12 months and the whole construction phase at 18 months, for example as three six-month periods, and grants no exceptions. A build that runs longer has to be redone as a two-closing loan.
In a two-closing transaction there are two separate sets of legal documents. B5-3.1-03 (dated 08/07/2019) says the first closing obtains the interim construction financing and may include buying the lot, and the second obtains the permanent financing once the improvements are complete. A modification may not be used to update the first note; the borrower signs a new one. The permanent lender may be a different company from the construction lender, and it underwrites the borrower on the terms of the permanent mortgage, as of the day that mortgage closes. Nothing about the first closing binds the second: not the rate, not the loan amount, and not the approval.
Federal disclosure law follows the same split. Regulation Z, at 12 CFR 1026.17(c)(6)(ii), lets a creditor that may provide both phases treat the construction and permanent phases "as either one transaction or more than one transaction." When the second closing is its own loan, you receive a second Loan Estimate and a second Closing Disclosure, with their own tolerance limits, and the Loan Estimate tolerance rules apply to that second set from scratch.
Rules side by side: Fannie Mae's single and two-closing sections and FHA's two products
FHA uses different names for the same two structures. Its Construction to Permanent product, in HUD Handbook 4000.1, is defined as combining a construction loan with a long-term mortgage "using a single mortgage closing prior to the start of construction." Its Building on Own Land product is the permanent financing of a newly built house on land the borrower owns, and it "may include the extinguishing of any construction loans," which makes it FHA's version of the second closing in a two-time close.
| Rule | Fannie Mae single closing | Fannie Mae two closings | FHA Construction to Permanent (one closing) | FHA Building on Own Land (permanent loan after a separate construction loan) |
|---|---|---|---|---|
| Permanent loan closes as | Purchase, or limited cash-out refinance if you owned the lot before the first draw | Limited cash-out refinance or cash-out refinance | Purchase limits apply: the maximum is the purchase LTV of the Adjusted Value | Purchase limits apply: the maximum is the purchase LTV of the Adjusted Value |
| Cash out to the borrower | Not eligible | Eligible if you held title to the lot for at least six months before the permanent loan closes; all other cash-out rules apply | Not described in the section; any money left in the construction escrow reduces the principal | None from added equity; you may be repaid your own documented spending on extras and out-of-pocket costs not in the builder's price |
| Value the loan is measured against | Purchase: lesser of lot price plus construction cost, or the "as completed" appraised value. Limited cash-out: the "as completed" appraised value | The current appraised value, as for any refinance | Lesser of the appraised value or the documented Acquisition Cost | Lesser of the appraised value or the documented Acquisition Cost, which here may include construction loan interest |
| Lot ownership time that matters | Whether you owned the lot at the first advance: yes means limited cash-out, no means purchase | Six months on title for cash-out; the 12-month age rule for a first mortgage being paid off also appears in the cash-out section | Land owned six months or less at case number assignment counts at the lesser of its cost or appraised value; longer, at appraised value | Same six-month land rule as the one-closing product |
| Construction period limit | No single period over 12 months; 18 months in total | None in the section | Amortization must start by the first of the month after 60 days from final inspection or certificate of occupancy | Not applicable; the construction loan is separate |
| Rate | Rate, amount, term and ARM-to-fixed can be modified at or before conversion, with re-underwriting | Set by the new note at the second closing | May float during construction within a written range, with a lock point, a maximum rate and a right to lock lower; you qualify at the maximum | Set at the permanent closing |
| Appraisal | Effective date within four months of the note, plus a completion report (Form 1004D); a new appraisal if value declined | A new appraisal; value acceptance (appraisal waiver) is unavailable for single-close and two-close loans | New Construction requirements apply (not compared here) | New Construction requirements apply (not compared here) |
| Credit documents | Four months old at the note; at conversion four months, or up to 18 months if LTV was 95% or less with a DU Approve/Eligible | Full underwriting on the permanent terms at the second closing | Standard FHA underwriting at the single closing | Standard FHA underwriting at the permanent closing |
Two rows hold what two closings give a borrower that one closing cannot: cash out at completion, and a construction phase with no 12-month or 18-month cap. Most of the rest is either the same rule written twice or a cost of the second closing. The FHA columns rest on HUD's product sections; the maximum LTV for FHA purchase transactions is 96.5 percent of the Adjusted Value for a borrower whose minimum decision credit score is 580 or higher, and 90 percent between 500 and 579, both in the same Update 18 handbook.
The value the permanent loan is measured against
One illustration household carries the arithmetic from here on. The lot cost $90,000, the builder's contract is $360,000, the appraiser values the finished house and lot at $480,000 "as completed," and the permanent loan is $400,000 on a 30-year fixed term. Fannie Mae's general rule in B2-1.2-01 (06/01/2022) measures a purchase against "the lower of the sales price or the current appraised value" and a refinance against "the current appraised value." B5-3.1-02 replaces the sales price with the lot price plus construction cost for a single-close purchase.
| Structure and lot status | Value used | LTV ratio |
|---|---|---|
| Single closing, lot bought with the construction loan (purchase) | $450,000, the lesser of $450,000 cost and $480,000 appraisal | 88.89% |
| Single closing, lot owned before the first draw (limited cash-out refinance) | $480,000 "as completed" appraisal | 83.33% |
| Two closings, permanent loan as limited cash-out refinance | $480,000 current appraisal | 83.33% |
| Two closings, permanent loan as cash-out refinance (lot on title six months or more) | $480,000 current appraisal | 83.33%, tested against the lower cash-out ceilings |
The 5.56 point gap between the first two rows comes from one fact, who held the lot when the first draw went out. Buying the lot inside a single-close loan caps the value at what you paid, so the $30,000 of equity the appraiser sees above cost does not lower the ratio. Owning the lot first, even by a few weeks, lets the full appraisal count. In a two-time close the permanent loan is always a refinance, so it always uses the appraisal, and the equity built during the build shows up if the market cooperates and disappears if it does not.
That last point cuts both ways. The appraisal at the second closing is a new one, ordered by the permanent lender, and B4-1.4-10 (06/03/2026) lists "construction-to-permanent loans (single-close and two-close)" among the transactions that cannot receive value acceptance. A single-close file is protected differently: if the completion report shows that the value declined, the lender orders a new appraisal and requalifies the borrower at the new LTV, so a falling market can still reach a single-close borrower before conversion. What happens when a finished house appraises below plan is covered in our guide to a refinance appraisal that comes in low.
FHA counts the lot by how long you have owned it
HUD does not use the "as completed" value alone. Both FHA products set the Adjusted Value at the lesser of the appraised value or the documented Acquisition Cost, then apply the purchase LTV. The Acquisition Cost includes the builder's price or the sum of subcontractor bids and materials, borrower-paid options not in that price, and the land, counted at the lesser of its cost or its appraised value if it was owned six months or less at case number assignment, or at appraised value if owned longer or received as an acceptable gift. The one-closing product adds closing costs on any interim financing of the land. The Building on Own Land product adds "interest and other costs associated with a construction loan," which matters in a two-time close because the construction loan has been charging interest on every draw.
Put a number on that interest. In this illustration the $360,000 is drawn in ten equal monthly draws of $36,000 and the construction loan charges 8.00% interest-only on the balance drawn; the 8.00% is an illustrative input, not a surveyed rate, because Freddie Mac's survey covers long-term mortgages only. Interest in month one is $240, in month ten $2,400, and the ten months total $13,200. Assume the lot, bought for $90,000, appraises at $110,000 on its own.
| Product and land holding | Acquisition Cost | Adjusted Value | Maximum at 96.5% |
|---|---|---|---|
| One closing, land held more than six months | $470,000 | $470,000 | $453,550 |
| One closing, land held six months or less | $450,000 | $450,000 | $434,250 |
| Building on Own Land, land held more than six months | $483,200 | $480,000 (appraisal is lower) | $463,200 |
| Building on Own Land, land held six months or less | $463,200 | $463,200 | $446,988 |
Two things move the ceiling. Holding the land past six months at case number assignment lets its $110,000 appraisal replace its $90,000 cost, which is worth $19,300 of borrowing capacity in the one-closing rows. And in the Building on Own Land rows the construction interest lifts the Acquisition Cost, so a borrower who already paid that interest can fold part of it into the permanent loan. Where the appraisal is the lower number, as in the third row, the interest stops helping. None of this is cash out: the Building on Own Land section says the borrower "may not receive cash back from the additional equity," apart from reimbursing documented extras and out-of-pocket expenses not included in the builder's price.
Three clocks on the lot and the construction note
The first clock runs only in a single closing, and it is a yes-or-no test rather than a count of months: did you hold legal title to the lot before the first advance of construction money? If you did, the loan is a limited cash-out refinance, and B5-3.1-02 says the proceeds pay off any liens on the lot and fund the construction, with "all other requirements for limited cash-out refinances" applying. If you did not, it is a purchase. Fannie Mae states plainly that cash-out refinances "are not eligible for single-closing construction-to-permanent mortgages."
The second clock is six months on title, and it governs cash-out in a two-time close. B5-3.1-03 makes the borrower eligible for a cash-out permanent loan only if they "held legal title to the lot for at least six months prior to the closing of the permanent mortgage." A lot bought two months before the build and a 9-month build together pass it. A lot bought at the construction closing and a 5-month build do not, and that permanent loan can only be a limited cash-out refinance. Our comparison of rate-and-term and cash-out refinances explains why the label changes the price and the ceiling, not only the cash.
The third clock is the one borrowers rarely hear about. Fannie Mae's cash-out section, B2-1.3-03 (12/10/2025), requires an existing first mortgage paid off through a cash-out refinance to be "at least 12 months old at the time of refinance, as measured by the note date of the existing loan to the note date of the new loan." The only exceptions it lists are subordinate liens and buying out a co-owner under a legal agreement. B5-3.1-03 adds that "all other standard cash-out refinance eligibility and underwriting requirements apply" and does not carve out the construction loan. Read as written, a two-time close on a 9 or 10 month build pays off a first lien that is less than 12 months old. Ask the permanent lender, before you choose cash-out, how it applies that rule to your construction note, and get the answer in writing.
A limited cash-out permanent loan has its own fences, in B2-1.3-02 (10/08/2025). It may pay off the construction loan and documented cost overruns incurred outside the interim financing, and those overruns must be paid directly to the builder at closing. Cash back to the borrower is capped at the greater of 1% of the new loan amount or $2,000. On the $400,000 illustration loan, 1% is $4,000, so up to $4,000 can come back without the loan becoming a cash-out refinance.
What the second closing repeats, line by line
A two-time close is two loans, and most of the fees on a Loan Estimate attach to a loan rather than to a house. The tally below uses round illustrative amounts, not averages, because fees vary by lender, county and state; your own two Loan Estimates supply the real figures. The structure is what matters: which lines appear twice, which appear once, and which are replaced by a cheaper item in the single-close version.
| Line | Single closing | Two closings: construction loan | Two closings: permanent loan | Why it repeats or not |
|---|---|---|---|---|
| Origination and underwriting | $1,500 | $1,500 | $1,500 | Two lenders, or one lender making two loans, each charging for its own |
| Appraisal | $650 | $650 | $650 | The permanent lender needs a new appraisal; value acceptance is excluded |
| Completion report (Form 1004D) | $200 | None | None | Single closing only; replaces the second appraisal |
| Lender's title policy | $1,400 | $1,200 | $1,400 | A new lender's policy on the new lien; ask the title agent whether a reissue or substitution rate applies |
| Settlement or closing fee | $900 | $900 | $900 | One closing appointment each |
| Recording | $150 | $150 | $150 | A new mortgage is recorded again; a single-close modification may also need recording |
| Credit report | $60 | $60 | $60 | Fresh underwriting at the permanent closing |
| Total | $4,860 | $4,460 | $4,660 | Two closings: $9,120, or $4,260 more |
The $4,260 is the cost of keeping the permanent rate open until the house is finished. It does not include prepaid interest and escrow deposits, which are timing items rather than fees: the prepaid daily interest collected at the permanent closing simply moves interest you would owe anyway. Title is the line with the most room to shrink. Lender's policy pricing varies by state and title agent, and the second policy may be priced lower if the first was issued recently; our guide to title insurance and settlement charges shows where that line sits on the form.
The single-close column carries costs of its own that the table cannot price. A rate commitment held through a 10 to 18 month build is priced by the lender, as a fee, a higher rate or points, and lock extension charges apply if the build runs past the lock. Those prices are not set by any rule in the sections read here. The rate lock fees and extensions guide explains where they show on the Loan Estimate and why the form does not show the price of an extension.
Rate exposure during a 9 to 12 month build, at four past survey windows
The reason to accept a second closing is to take the rate available when the house is finished instead of the one available when the foundation was poured. Whether that helps depends entirely on which way rates went during the build, and the weekly 30-year average in Freddie Mac's Primary Mortgage Market Survey history file shows four recent windows of 9 to 11 months with very different results. The survey reports an average, not a quote; our explainer on how the PMMS works covers what the weekly number does and does not measure.
| Build window (survey weeks) | Start rate | End rate | Range inside the window | Payment at start rate | Payment at end rate | Monthly change |
|---|---|---|---|---|---|---|
| January 6, 2022 to December 1, 2022 (10.8 months) | 3.22% | 6.49% | 3.22% to 7.08% (October 27, 2022) | $1,734.25 | $2,525.64 | +$791.40 |
| November 2, 2023 to October 3, 2024 (11.0 months) | 7.76% | 6.12% | 6.08% (September 26, 2024) to 7.76% | $2,868.41 | $2,429.15 | -$439.26 |
| February 6, 2025 to December 4, 2025 (9.9 months) | 6.89% | 6.19% | 6.17% (October 30, 2025) to 6.89% | $2,631.73 | $2,447.28 | -$184.44 |
| January 8, 2026 to October 29, 2026 (9.7 months) | 6.16% | 7.24% | 5.98% (February 26, 2026) to 7.40% (October 8, 2026) | $2,439.50 | $2,725.99 | +$286.49 |
Two of the four windows rewarded waiting and two punished it. The 2022 window is the extreme one: a borrower who fixed 3.22% at the construction closing kept it, while one who waited for a second closing faced 6.49% and a payment $791.40 higher. In the 2023 to 2024 window the opposite happened, and a borrower who fixed 7.76% at the start paid $439.26 a month more than one who closed the permanent loan in October 2024. The 2026 window shows how much can happen inside a single build: the average fell to 5.98% in late February and rose to 7.40% by early October, a 1.42 point swing that is worth $376.46 a month on this loan, depending only on which week the permanent loan happened to close.
Set those monthly changes against the $4,260 of extra closing costs and the break-even month follows directly, on a $400,000 balance, a new 30-year term and a seven-year stay. In the 2023 to 2024 window, $4,260 divided by $439.26 is 9.7, so the second closing pays for itself in month 10. In the 2025 window, $4,260 divided by $184.44 is 23.1, so it breaks even in month 24. In the 2022 and 2026 windows there is no break-even month: the second closing costs more every month and also cost $4,260 to arrange. These are past windows, and they say nothing about the direction of the next one; they show the size of the exposure, which is what a borrower is choosing to carry.
The same build, closed 11 months apart in 2023 and 2024
Hold the illustration household in the 2023 to 2024 window: a $400,000 permanent loan on a 30-year term, a seven-year stay, and a builder who finishes in 11 months. Version one is a single close fixed at the November 2, 2023 survey average of 7.76%, with no modification at conversion, and $4,860 in closing costs. Version two is a two-time close whose permanent loan closes at the October 3, 2024 average of 6.12%, with $9,120 in closing costs across both closings. Split the result into its two causes. The rate effect is $439.26 a month, or $36,898 of payments over 84 months. The cost effect runs the other way: version two paid $4,260 more to close. The net is $32,638 in version two's favor by month 84, with the break-even in month 10. The balances tell the same story: after 84 payments, version one owes $368,696 and version two owes $359,320, because a lower rate also sends more of each payment to principal. Over those 84 months version one pays $209,642 in interest and version two pays $163,369. Move the same household to the 2022 window and the signs flip. A single close fixed at 3.22% pays $1,734.25 a month; a two-time close at 6.49% pays $2,525.64, or $66,478 more over 84 months, on top of the $4,260 in extra closing costs, and never breaks even. Neither result could be known at the construction closing.
A single-close lock is less fixed than it looks
The table above compares a rate fixed at the start with the market rate at the end, but neither Fannie Mae nor FHA forces a single-close borrower to keep the first rate. B5-3.1-02 lets the loan be modified "prior to or at the time of conversion" in four terms only: interest rate, loan amount, loan term, and amortization type, and the only amortization change allowed is from adjustable to fixed. Any other change requires a two-closing transaction. The modified loan is underwritten on its new terms and resubmitted to Desktop Underwriter unless the change is within its tolerances, and a loan amount may rise only to cover documented increases in construction cost.
Whether a lender offers that modification, and at what price, is a matter of contract. Fannie Mae's rule makes it possible; it does not make the lender agree. Ask before the first closing whether the construction loan agreement includes a float-down or a modification option at conversion, what it costs, and what market move triggers it. FHA builds the option into its rule: the agreement must document the range in which the rate may float during construction, the point of lock-in and a maximum permanent rate, and must permit the borrower to lock in at a lower rate if one is available and they have not already locked. HUD requires the lender to qualify the borrower at that maximum rate.
A modification at conversion also reopens underwriting in ways a simple lock does not. If income, employment and credit documents are older than four months at conversion, Fannie Mae accepts them up to 18 months only when the loan had an LTV, CLTV and HCLTV of 95% or less and a DU Approve/Eligible at the original closing, and only if the rate or amount did not change beyond the DU resubmission tolerances. Otherwise the borrower is requalified on fresh documents. Someone who changed jobs during the build, or whose debts grew with furniture and appliances for the new house, can find that a rate modification triggers a review the original lock would have avoided.
Disclosure timing has its own rule for new construction. Under 12 CFR 1026.19(e)(3)(iv)(F), when the creditor reasonably expects settlement more than 60 days after the Loan Estimate, it may issue a revised one, but only if the original stated clearly that it may do so at any time prior to 60 days before consummation. And when a rate was not locked at the Loan Estimate, the creditor must provide a revised version no later than three business days after the rate is locked. On a long build, check the first Loan Estimate for the 60-day statement: without it, the lender has far less room to revise the estimated costs later.
Refinancing again after a one-time close has converted
Once a single-close loan converts, it is an ordinary permanent mortgage, and a later refinance follows the ordinary rules. The useful detail is the date the rules count from. B5-3.1-02 defines the note date of a single-close loan as "the closing date of the construction loan," so the 12 months that B2-1.3-03 requires before a cash-out refinance can pay off a first mortgage are measured from the construction closing, not from the conversion. On a 10-month build, a converted loan is 12 months old about two months after the house is finished.
A limited cash-out refinance of the converted loan has no seasoning requirement of that kind, but it carries a full set of closing costs, and the decision to do it is a plain break-even question. If a single-close borrower locked at the 2023 window's 7.76% start and later saw rates near the 6.12% of October 2024, the comparison is between the cost of a new loan and the $439.26 monthly difference, run against a new 30-year term. Our guide to how soon you can refinance collects the waiting periods for each loan program, and the break-even explainer shows how to separate a lower rate from the cost of restarting the term.
The appraisal question also changes after conversion. The value acceptance exclusion in B4-1.4-10 names construction-to-permanent loans; a refinance of a finished, converted loan is no longer one. The same section notes that Desktop Underwriter "may offer value acceptance on a recently constructed property" when there is an existing "as is" prior appraisal of it. Whether an offer appears is up to DU; our guide to refinancing without an appraisal lists the other tests the file has to pass first.
Picking the structure before the first draw
The choice has to be made before construction starts, because a single-close loan cannot be turned into a two-close loan without paying off the first note, and a two-close borrower has no permanent commitment to fall back on. On the rules above, the decision rests on four facts you know at the start:
- Cash out at completion. If you need equity out of the finished house, only a two-time close can deliver it under Fannie Mae, and only with six months on the lot title, subject to the lender's reading of the 12-month first mortgage rule. Neither FHA product read here describes cash out to the borrower.
- Who owns the lot at the first draw. If you will own it before construction money is advanced, a single close uses the full "as completed" value; if the lot is bought inside the loan, the value is capped at cost. Under FHA, land held more than six months at case number assignment counts at appraised value.
- How long the build will run. A Fannie Mae single close cannot run past 18 months of construction, with no exceptions. A builder's schedule with weather or permit risk past that point pushes the file to two closings anyway.
- How much rate exposure you can carry. On a $400,000 loan, the four survey windows above moved the payment by between $184.44 and $791.40 a month. A two-time close carries that exposure, plus about $4,260 in repeated costs on the illustration figures; a single close with a modification or float-down option shifts some of it to a price paid up front.
Once both structures are quoted, put each one through the Stay or Refi Calculator with its full closing costs: the single-close quote at its locked rate, and the two-close quote at the permanent rate you would accept, to see which month each one starts to win. For a plain amortization schedule on either loan, the CalculatorVillage amortization calculator prints the balance at any month.
What the lender will ask for at the permanent closing
- The deed or closing statement for the lot, showing the date title passed to you; it decides purchase versus limited cash-out in a single close, the six-month cash-out test in a two-time close, and FHA's land value.
- The construction loan note and agreement, with its note date, maturity, any extension terms, and any float-down or modification clause.
- The builder's contract, change orders, and receipts for borrower-paid extras or overruns paid outside the construction loan.
- The final draw statement and the construction loan payoff letter, including the interest charged during the build.
- The certificate of occupancy or final inspection, and the appraiser's completion report (Form 1004D) or the new appraisal.
- Both Loan Estimates, if you have them, so the second closing's fees can be compared line by line with the first.
Before and after conversion: construction loan questions
Is the second closing on a two-time close a refinance?
Yes. Under Fannie Mae Selling Guide B5-3.1-03 (dated August 7, 2019), the permanent mortgage in a two-closing transaction closes as a limited cash-out refinance or a cash-out refinance, on a new note, and it may come from a different lender than the construction loan.
Can I take cash out when my construction loan converts?
Not on a Fannie Mae single-closing loan, which B5-3.1-02 limits to a purchase or a limited cash-out refinance. A two-closing permanent loan can be a cash-out refinance if you held title to the lot for at least six months before it closes, and the cash-out section also has a 12-month age rule for a first mortgage being paid off, which you should ask the lender to apply to your construction note.
Does a construction-to-permanent loan need a new appraisal at the end?
A single-close loan needs a completion report (Form 1004D) at completion, and a new appraisal only if the report shows that the value declined. A two-closing permanent loan is appraised again, because Fannie Mae's value acceptance section, B4-1.4-10 (June 3, 2026), excludes both single-close and two-close construction-to-permanent loans.
How much more does a two-time close cost?
Roughly the cost of a second loan closing, because origination, appraisal, lender's title policy, settlement, recording and credit report repeat. On this guide's illustrative amounts for a $400,000 loan, one closing costs $4,860 and two cost $9,120, a difference of $4,260; your own Loan Estimates supply the actual figures.
Can the rate change on a one-time close construction loan?
It can. Fannie Mae allows the interest rate, loan amount, term and an ARM-to-fixed change to be modified at or before conversion, with re-underwriting, and FHA requires a written range, a maximum rate and a right to lock lower if you have not locked. Whether your lender offers a lower rate at conversion depends on your loan agreement.
How long can the construction phase of a one-time close last?
Under Fannie Mae B5-3.1-02, no single construction period may exceed 12 months and the total may not exceed 18 months, with no exceptions. A longer build must be handled as a two-closing transaction. For FHA, amortization must begin by the first of the month after 60 days from the final inspection or the issuance of the certificate of occupancy.
Sources and verification
- Fannie Mae Selling Guide, B5-3.1-01 Conversion of Construction-to-Permanent Financing: Overview (06/04/2025): One or two closings; title to the lot; liens cleared before delivery; attached condo units and co-ops ineligible. Checked October 31, 2026.
- Fannie Mae Selling Guide, B5-3.1-02 Single-Closing Transactions (05/06/2026): 12-month and 18-month construction periods; purchase or limited cash-out only; LTV by lot ownership at first advance; modifications at conversion; four and 18 month document ages; Form 1004D; note date defined as the construction loan closing date. Checked October 31, 2026.
- Fannie Mae Selling Guide, B5-3.1-03 Two-Closing Transactions (08/07/2019): Two sets of documents and a new note; limited cash-out or cash-out; six months of title to the lot for cash-out; other cash-out rules apply. Checked October 31, 2026.
- Fannie Mae Selling Guide, B2-1.3-02 Limited Cash-Out Refinance Transactions (10/08/2025): Payoff of a construction loan and overruns paid to the builder; cash back up to the greater of 1% of the new loan or $2,000. Checked October 31, 2026.
- Fannie Mae Selling Guide, B2-1.3-03 Cash-Out Refinance Transactions (12/10/2025): Existing first mortgage at least 12 months old, note date to note date, with exceptions for subordinate liens and co-owner buyouts; six months on title. Checked October 31, 2026.
- Fannie Mae Selling Guide, B2-1.2-01 Loan-to-Value (LTV) Ratios (06/01/2022): Purchase value is the lower of sales price or appraised value; refinance value is the current appraised value. Checked October 31, 2026.
- Fannie Mae Selling Guide, B4-1.4-10 Value Acceptance (06/03/2026): Proposed construction and construction-to-permanent loans (single-close and two-close) ineligible; note on recently constructed properties with a prior "as is" appraisal. Checked October 31, 2026.
- HUD Handbook 4000.1, Update 18 tracked-changes copy (last revised 8/12/2026): Construction to Permanent (09/20/2021): Acquisition Cost, six-month land rule, floating rate agreement, qualifying at the maximum rate, amortization start. Building on Own Land (06/17/2019): construction loan interest in Acquisition Cost, no cash back from added equity. Purchase maximum LTV of 96.5 percent at a 580 or higher minimum decision credit score. Checked October 31, 2026.
- 12 CFR 1026.43, Regulation Z ability-to-repay exemptions (eCFR, Title 12 up to date as of October 29, 2026): Exemption for a construction phase of 12 months or less of a construction-to-permanent loan. Checked October 31, 2026.
- 12 CFR 1026.19 and 1026.17, Regulation Z disclosure rules (eCFR, Title 12 up to date as of October 29, 2026): 1026.19(e)(3)(iv)(F) revised Loan Estimate when new construction settles more than 60 days out; (D) revised estimate within three business days of a rate lock; 1026.17(c)(6)(ii) one or more transactions for construction and permanent phases. Checked October 31, 2026.
- Freddie Mac Primary Mortgage Market Survey, historical weekly data (PMMS_history.csv): 30-year fixed averages for the weeks of January 6, 2022 (3.22%), October 27, 2022 (7.08%), December 1, 2022 (6.49%), November 2, 2023 (7.76%), September 26, 2024 (6.08%), October 3, 2024 (6.12%), February 6, 2025 (6.89%), October 30, 2025 (6.17%), December 4, 2025 (6.19%), January 8, 2026 (6.16%), February 26, 2026 (5.98%), October 8, 2026 (7.40%) and October 29, 2026 (7.24%). Checked October 31, 2026.
No loan is offered here, and none of it is legal, tax or credit advice. A lender may read the program rules more strictly than they are stated on this page. Fannie Mae's Eligibility Matrix, which sets the maximum LTV for each transaction type, was not read for this guide, and neither was Freddie Mac's Guide, whose construction rules can differ; VA and USDA construction rules are not covered. The 12-month first mortgage rule's application to a two-closing construction note is stated as the Selling Guide words it; confirm your lender's reading. All closing cost amounts, the construction loan rate and the household figures are illustrations, and survey rates are published weekly averages used for arithmetic, not quotes or predictions.